Bid Title: Contract for Purchase of Substation Steel, Bus and Switch Package
Category: Bid Opportunities
Status: Closed

Description:

Sealed Bids will be received by the Department of Utilities of the City of Fremont, Nebraska at the office of the City Clerk, 400 East Military Avenue, Fremont, Nebraska, until 2:00 PM CDT, on Tuesday, September 19, 2023, for the purchase of the following:

 Substation Steel, Bus and Switch Package 

The Work includes furnishing a complete material and equipment package including all specified substation steel, bus, switches and associated parts and accessories. Deliver to site, City of Fremont, NE. 

Bids received after the above specified time for opening will be returned unopened to the sender. 

Specifications are available by request at the office of the Electrical Engineering, 3000 E. 1st St, Fremont, Nebraska, 68025 (Phone 402-727-2613). 

Each proposal shall be sealed in an envelope marked “BID FOR SUBSTATION STEEL, BUS AND SWITCH PACKAGE”. 

Each bidder shall submit with each proposal a certified check or bid bond by a nationally recognized company, countersigned by a resident agent, payable to the City Treasurer of the City of Fremont, Nebraska, the amount of which shall be not less than five percent (5%) of the bid price and which shall guarantee good faith on the part of the bidder and the entering into Contract within 15 days after notification of acceptance at the price bid. 

A performance bond in the amount of 100% of the Contract price will be required of the successful bidder at the time of execution of Contract. 

Bids will be evaluated by the City, based on quality, time required for delivery, and experience of the Packager. The City reserves the right to select the bid which best suits its needs whether price is the lowest or not, and also reserves the right to reject any or all bids and waive irregularities therein, and all bidders must agree that such rejection shall be without liability on the part of the City for any penalty brought by any bidder because of such rejections; and the filing of any bid in response to this invitation shall constitute an agreement of the bidder to these conditions. 

Bidders may not withdraw bids for a period of sixty (60) days after the date of the bid opening. 

City of Fremont, Nebraska Joey Spellerberg, Mayor 

Attest: Tyler Ficken City Clerk

Publication Date/Time:
8/21/2023 8:00 AM
Publication Information:
8/26/23; 9/2/23; 9/9/23
Closing Date/Time:
9/19/2023 2:00 PM
Related Documents:

Return To Main Bid Postings Page